# The Ferrybridge Multifuel 2 Power Station Order 2015, Paragraph 19: Construction traffic routing and management plan

Extent: E+W+S

(1) The authorised development must not commence until a written construction traffic routing and management plan has been submitted to and, after consultation with the relevant highway authorities, approved by the planning authority.
(2) The plan submitted and approved must be in accordance with the principles set out in chapter 7 of the environmental statement and the construction staff travel plan framework contained in Appendix 7B to the environmental statement.
(3) The plan submitted and approved must include—
(a) details of the routes to be used for the delivery of construction materials and any temporary signage to identify routes and promote their safe use, including details of the access points to the construction site to be used by light goods vehicles and heavy goods vehicles;
(b) details of the routing strategy and procedures for the notification and conveyance of abnormal indivisible loads, including agreed routes, the numbers of abnormal loads to be delivered by road and measures to mitigate traffic impact;
(c) the construction programme;
(d) any necessary measures for the temporary protection of carriageway surfaces, the protection of statutory undertakers’ plant and equipment and any temporary removal of street furniture;
(e) measures to promote the use of sustainable transport modes by construction personnel in order to minimise the overall traffic impact and promote sustainable transport modes;
(f) details of parking for construction personnel within the construction site; and
(g) details of a co-ordinator to be appointed to manage and monitor the implementation of the plan, including date of appointment, responsibilities and hours of work.
(4) Notices must be erected and maintained throughout the period of construction at every entrance to and exit from the construction site, indicating to drivers the approved routes for traffic entering and leaving the construction site.
(5) The plan must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2015/1832/schedule/2/paragraph/19 (the official version)
Page: https://openlegislation.uk/ferrybridge-multifuel-2-power-station-order-2015/schedule-2/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.