# The Ferrybridge Multifuel 2 Power Station Order 2015, Paragraph 3: Fuel type

Extent: E+W+S

(1) Only fuel of a type specified in the environmental permit may be combusted in the boilers of the authorised development.
(2) Except for purposes of the start-up or support firing of a boiler, only waste derived fuel may be combusted in the boilers of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2015/1832/schedule/2/paragraph/3 (the official version)
Page: https://openlegislation.uk/ferrybridge-multifuel-2-power-station-order-2015/schedule-2/paragraph-3