# The Ferrybridge Multifuel 2 Power Station Order 2015, Paragraph 44: Aviation warning lighting

Extent: E+W+S

(1) The authorised development must not commence until written details of the aviation warning lighting to be installed on the emissions stack comprised in Work No. 1A and each crane required for the construction of the authorised development which has a height of 60m or greater have been submitted to and approved by the planning authority.
(2) The aviation warning lighting must be installed and operated in accordance with the approved details.

---