# The Ferrybridge Multifuel 2 Power Station Order 2015, Paragraph 45: Air safety

Extent: E+W+S

The authorised development must not commence until written details of the information that is required by the Defence Geographic Centre of the Ministry of Defence to chart the site for civil aviation purposes have been submitted to and approved by the planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2015/1832/schedule/2/paragraph/45 (the official version)
Page: https://openlegislation.uk/ferrybridge-multifuel-2-power-station-order-2015/schedule-2/paragraph-45
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.