{
  "url": "https://openlegislation.uk/ferrybridge-multifuel-2-power-station-order-2015/schedule-2/paragraph-46",
  "json_url": "https://openlegislation.uk/ferrybridge-multifuel-2-power-station-order-2015/schedule-2/paragraph-46.json",
  "legislation": "uksi/2015/1832",
  "legislation_title": "The Ferrybridge Multifuel 2 Power Station Order 2015",
  "legislation_url": "https://openlegislation.uk/ferrybridge-multifuel-2-power-station-order-2015",
  "path": "schedule/2/paragraph/46",
  "kind": "paragraph",
  "number": "46",
  "heading": "Site security",
  "text": "(1) The authorised development must not be commissioned until a written scheme detailing security measures to minimise the risk of crime within the Order limits has been submitted to and, after consultation with West Yorkshire Police, approved by the planning authority.\n(2) The approved scheme must be maintained and operated throughout the operation and decommissioning of the authorised development.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 46 in force at 19.11.2015, see art. 1(2)"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2015/1832/schedule/2/paragraph/46",
    "retrieved_at": "2026-10-28T23:31:05.805955+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}