# The Ferrybridge Multifuel 2 Power Station Order 2015, Paragraph 48: Employment, skills and training plan

Extent: E+W+S

(1) Work No. 1 must not commence until a written plan detailing arrangements to promote employment, skills and training development opportunities for local residents has been submitted to and approved by the planning authority.
(2) The approved plan must be implemented and maintained during the construction and operation of Work No.1.

---
Source: https://www.legislation.gov.uk/uksi/2015/1832/schedule/2/paragraph/48 (the official version)
Page: https://openlegislation.uk/ferrybridge-multifuel-2-power-station-order-2015/schedule-2/paragraph-48
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.