# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 25: Reporting of engaged agents, contractors and vessels

Extent: E+W

(1) The undertaker must provide the following information to the MMO—
(a) the name, company number, address and function of any agent, contractor or subcontractor appointed to engage in the licensed activities not less than ten working days prior to such agent or contractor commencing any licensed activity; and
(b) each week during the construction of the authorised development a list of the vessels currently and to be used in relation to the licensed activities, including the master’s name, vessel type, vessel IMO number and vessel owner or operating company.
(2) Any changes to the supplied details must be notified to the MMO in writing not less than 24 hours prior to the agent, contractor or vessel engaging in the licensed activities.
(3) The undertaker must notify the MMO in writing not less than 24 hours prior to the commencement of major component exchanges, ladder replacements or cable related works—
(a) any agents, contractors or subcontractors that will carry out such works; and
(b) any vessel proposed to be used for such works, including the master’s name, vessel type, vessel IMO number and vessel owner or operating company.

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/10/paragraph/25 (the official version)
Page: https://openlegislation.uk/five-estuaries-offshore-wind-farm-order-2025/schedule-10/paragraph-25
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.