# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 33: Stages of construction

Extent: E+W

(1) The licenced activities must not be commenced until a written scheme setting out the stages of construction of the authorised development seaward of MHWS has been submitted to and approved by the MMO in writing.
(2) The scheme must be implemented as approved.
(3) The written scheme referred to in sub-paragraph (1) must be submitted to the MMO in writing four months prior to the planned commencement of the licenced activities.

---