# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 9


Any amendments to or variations from the approved details, plan or scheme must be in accordance with the principles and assessments set out in the environmental statement. Such agreement may only be given in relation to changes where it has been demonstrated to the satisfaction of the MMO that it is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

---