(1) Offshore substation platform foundation structures forming part of the authorised scheme must be one of either monopile foundations or jacket foundations.
(2) No offshore substation platform with a piled foundation may—
(a) employ more than 6 piles per foundation;
(b) in the case of monopile foundations, exceed a monopile diameter of 15 metres; or
(c) in the case of a two or more pile foundation, exceed a pile diameter of 4 metres per pile.

---