# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 5

Extent: E+W

The surveys required under paragraph 4 must include—
(a) detailed surveys of the habitat, fauna, and flora within the red line boundary of the proposed compensation measure and suitable buffer area, including access points, undertaken at the optimal time(s) for each relevant species or habitat; and
(b) following analysis of findings, development of any necessary additional mitigation measures required to inform the LIMP, including monitoring post-installation to determine the success of the mitigation.

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/13/part/1/paragraph/5 (the official version)