# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 13: Ground water monitoring

Extent: E+W

(1) No stage of the onshore works for which a groundwater monitoring plan is required in accordance with the outline groundwater monitoring plan, must be commenced until, for that stage a groundwater monitoring plan has been submitted to and approved by the discharging authority.
(2) Sub-paragraph (1) does not apply to any works or surveying and investigation necessary to inform the preparation of a groundwater monitoring plan.
(3) Any plan approved under sub-paragraph (1) must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/2/paragraph/13 (the official version)
Page: https://openlegislation.uk/five-estuaries-offshore-wind-farm-order-2025/schedule-2/paragraph-13/enacted