# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 1: Time limits

Extent: E+W

The authorised development must commence no later than the expiration of seven years beginning with the date this Order comes into force.

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/2/part/1/paragraph/1 (the official version)
Page: https://openlegislation.uk/five-estuaries-offshore-wind-farm-order-2025/schedule-2/part-1/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.