(1) The onshore works must not be commenced until notification has been submitted to the discharging authority detailing whether the onshore works will be constructed—
(a) in a single stage; or
(b) in two or more stages.
(2) The onshore works must not be commenced until details of the stages of the onshore works have been submitted to the discharging authority.
(3) The onshore works must be constructed in accordance with the details provided under sub-paragraph (2) of this requirement.

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/2/part/1/paragraph/4 (the official version)