# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 100: Acquisition of land and protection of apparatus

Extent: E+W

Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference to this Order, the undertaker must not acquire any interest in land or any apparatus or override any easement or other interest of North Falls otherwise than by agreement, such agreement not to be unreasonably withheld or delayed.

---