# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 105: Design collaboration

Extent: E+W

The undertaker and North Falls must each act in good faith and use reasonable endeavours to co-operate with, and provide assistance to, each other as may be required to give effect to the provisions of this Part.

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/9/paragraph/105 (the official version)
Page: https://openlegislation.uk/five-estuaries-offshore-wind-farm-order-2025/schedule-9/paragraph-105
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.