# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 112: Services

Extent: E+W

Without prejudice to the generality of any other protection afforded to the PLA elsewhere in the Order, the undertaker must not decommission or remove any utilities and services and any right of the owner of the utilities and services to access and maintain the utilities and services must not be extinguished until alternative utilities and services have been constructed and are in operation serving the apparatus to the PLA’s reasonable satisfaction.

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/9/paragraph/112 (the official version)
Page: https://openlegislation.uk/five-estuaries-offshore-wind-farm-order-2025/schedule-9/paragraph-112
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.