If, following the results of any geophysical surveys carried out using multi-beam echo sounder survey (MBES), it is confirmed that cable exposure has occurred within the Area of Interest, the undertaker will notify the PLA as soon as reasonably practicable and in any event no later than 2 business days after the undertaker confirms any exposure has occurred.

---