# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 120


Unless otherwise agreed in writing with the PLA, the undertaker will carry out the following arrangements for the carrying out the remediation works as set out in paragraph 121 below.

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/9/paragraph/120 (the official version)
Page: https://openlegislation.uk/five-estuaries-offshore-wind-farm-order-2025/schedule-9/paragraph-120
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.