# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 121


(1) The undertaker will re-bury the cables to the required specification to achieve the requirements of paragraph 116(a).
(2) Following the completion of the works in sub-paragraph (1), if it is identified by the undertaker or the PLA (following inspection) that the required specification is not achieved, then the undertaker will remove the cable without unreasonable delay and thereafter relay a new cable pursuant to an updated cable specification and installation plan which updated cable specification and installation plan specifically identifies and addresses why the previous cable burial was not successful, how that has been addressed and what measures are to be used in relaying the cable to prevent the failure reoccurring.
(3) The undertaker will consult the PLA on the draft updated cable specification and installation plan required under sub-paragraph (2) and the provisions of both this paragraph and paragraph 117 will apply to that updated cable specification and installation plan.
(4) The steps in this paragraph shall be repeated until the requirement in paragraph 116(a) is achieved or the cable is permanently removed from the Area of Interest.

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/9/paragraph/121 (the official version)
Page: https://openlegislation.uk/five-estuaries-offshore-wind-farm-order-2025/schedule-9/paragraph-121
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.