# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 125: Application

Extent: E+W

The provisions of this Part of this Schedule have effect in relation to the works (as defined under paragraph 126 unless otherwise agreed in writing between the undertaker and Essex County Council in its capacity as the local highway authority.

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/9/paragraph/125 (the official version)