# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 141: Access

Extent: E+W

(1) Access for Anglian Water or any person acting under its instruction, including access for vehicles and plant, to the Anglian Water Property over Plot 01-002 and to any apparatus, utilities and services will not be extinguished or prevented and must not be unreasonably restricted or delayed by the undertaker during the construction, operation, maintenance or decommissioning of the Authorised Development in accordance with sub-paragraphs (2) and (3).
(2) Unreasonable delay or restriction in sub-paragraph (1) will not prevent the temporary restriction of access for other users (including access by the public) or the control or marshalling of access to facilitate the safe movement of large vehicles or plant or the carrying out of works to the access route by the undertaker, subject to the provisions of sub-paragraphs (2) and (3) of this paragraph.
(3) Where any part of the access to the Anglian Water Property is restricted or controlled by the undertaker, any physical measures must be agreed by Anglian Water (acting reasonably) prior to the implementation. The undertaker must provide access to the Anglian Water Property on request from Anglian Water or any person acting under its instruction and take steps (as soon as reasonably practicable) to allow access to and from the Anglian Water Property through or around that restriction or physical measure.

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/9/paragraph/141 (the official version)
Page: https://openlegislation.uk/five-estuaries-offshore-wind-farm-order-2025/schedule-9/paragraph-141
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.