# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 63

Extent: E+W

The undertaker must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 43 (certification of plans, etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail in the format reasonably specified by Network Rail (acting reasonably).

---
Source: https://www.legislation.gov.uk/uksi/2025/1376/schedule/9/paragraph/63 (the official version)
Page: https://openlegislation.uk/five-estuaries-offshore-wind-farm-order-2025/schedule-9/paragraph-63
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

