# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 89


The draft cable specification and installation plan referred to in paragraph 88 must set out for Work No. 2—
(a) the proposed cable burial depth(s);
(b) the proposed cable burial methods;
(c) any cable protection proposed including type, volume and anticipated locations; and
(d) the proposed programme of work for cable burial.

---