# The Five Estuaries Offshore Wind Farm Order 2025, Paragraph 90: Approvals and refusals

Extent: E+W

London Gateway must issue any approval or refusal of a draft plan submitted to it in accordance with paragraph 88 within 28 days of the date of submission of that draft unless any other period is agreed with the undertaker.

---