# The Galloper Wind Farm Order 2013, Article 31: Arbitration

Extent: E+W+S

Any difference under any provision of this Order, unless otherwise provided for, shall be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the Secretary of State.

---
Source: https://www.legislation.gov.uk/uksi/2013/1203/article/31 (the official version)