# The Galloper Wind Farm Order 2013, Paragraph 24: Fencing and other means of enclosure

Extent: E+W+S

(1) No part of the connection works or the transmission works shall commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure for the relevant part of the relevant works have been submitted to and approved by the relevant planning authority.
(2) All permanent and temporary fences, walls or other means of enclosure must be constructed in accordance with the approved details, unless otherwise agreed by the relevant planning authority.
(3) All construction sites must remain securely fenced at all times during construction of the relevant works.
(4) Any temporary fencing must be removed on completion of the relevant works.
(5) Any approved permanent fencing in relation to Work No. 6 or Work No. 10 or the sealing end compound must be completed before the relevant work or compound is brought into use.

---
Source: https://www.legislation.gov.uk/uksi/2013/1203/schedule/1/paragraph/24 (the official version)
Page: https://openlegislation.uk/galloper-wind-farm-order-2013/schedule-1/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.