  "url": "https://openlegislation.uk/galloper-wind-farm-order-2013/schedule-1/paragraph-28",
  "json_url": "https://openlegislation.uk/galloper-wind-farm-order-2013/schedule-1/paragraph-28.json",
  "legislation": "uksi/2013/1203",
  "legislation_title": "The Galloper Wind Farm Order 2013",
  "legislation_url": "https://openlegislation.uk/galloper-wind-farm-order-2013",
  "path": "schedule/1/paragraph/28",
  "kind": "paragraph",
  "number": "28",
  "heading": "Construction code of practice",
  "text": "No part of the connection works or the transmission works shall be commenced until a construction code of practice relating to the relevant part of the relevant works has been submitted to and, after consultation with the highway authority and Natural England, approved by the relevant planning authority in relation to the relevant part of the relevant works. The code shall cover all the subject areas set out in the final draft code submitted as part of the examination and as certified by the Secretary of State and any other matters the relevant planning authority reasonably requires. The code approved in relation to the relevant part of the relevant works shall be followed in relation to those works, unless otherwise agreed by the relevant planning authority.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 para. 28 in force at 15.6.2013, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2013/1203/schedule/1/paragraph/28",
    "retrieved_at": "2026-10-29T00:54:08.546344+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}