# The Galloper Wind Farm Order 2013, Part 2: Ancillary works

Extent: E+W+S

Seaward of mean low water spring tides, works comprising—
(a) temporary moorings or other means of accommodating vessels in the construction and/or maintenance of the authorised development;
(b) buoys, beacons, fenders and other navigational warning or ship impact protection works; and
(c) temporary works for the benefit or protection of land or structures affected by the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2013/1203/schedule/1/part/2 (the official version)
Page: https://openlegislation.uk/galloper-wind-farm-order-2013/schedule-1/part-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.