# The Galloper Wind Farm Order 2013, Paragraph 13: Seasonal restrictions

Extent: E+W+S

(1) No piling of monopile foundations or other foundation piling in the course of construction of the authorised scheme shall take place in array area C during the relevant peak sole spawning season (the maximum period being 1st April to 15th May), unless otherwise agreed with the MMO, following consultation with Natural England and JNCC.
(2) No piling of monopile foundations or other foundation piling in the course of construction of the authorised scheme shall take place in array area B during the relevant peak herring spawning season (the maximum period being 1st November to 31st December), unless otherwise agreed with the MMO, following consultation with Natural England and JNCC.

---
Source: https://www.legislation.gov.uk/uksi/2013/1203/schedule/2/paragraph/13 (the official version)
Page: https://openlegislation.uk/galloper-wind-farm-order-2013/schedule-2/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.