# Gas Act 1965, Paragraph 1


(1) At any time after an application has been made for the consent of the Secretary of State to the carrying out of any controlled operations for which planning permission is required but has not been granted any person concerned may apply to the local planning authority for a certificate under this Schedule as respects those controlled operations.
(2) Where such an application is made the local planning authority shall issue to the applicant a certificate stating that planning permission for the carrying out of the controlled operations could, or could not, reasonably have been expected to have been granted if the land had not been comprised in the storage area or protective area.
(3) Where, in the opinion of the local planning authority, planning permission might reasonably have been expected to be granted but would only have been granted subject to conditions, the certificate shall specify those conditions in addition to the other matters required to be contained in the certificate.
(4) On issuing the certificate, the local planning authority shall serve a copy of the certificate on the public gas supplier.

---
Source: https://www.legislation.gov.uk/ukpga/1965/36/schedule/3/paragraph/1 (the official version)
Page: https://openlegislation.uk/gas-act-1965/schedule-3/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.