For the purposes of subsection (2) of section 6, the Director may determine as the relevant date a date which is—
(a) not earlier than 1st April 1998;
(b) after the date determined by him in respect of the area specified in Part V of the Schedule;
(c) at least four months after the Director’s proposal to determine a date for the purposes of that subsection is notified under article 5 below; and
(d) at least two months after the date on which his determination is made.

---
Source: https://www.legislation.gov.uk/uksi/1997/826/article/4 (the official version)
Page: https://openlegislation.uk/gas-extent-of-domestic-supply-licences-order-1997/article-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.