Regulation 4
The following Schedule shall be substituted for Schedule 1 to the Principal Regulations–
“SCHEDULE 1
(FEES)
Regulation 5(1) and (10)
(1) Measuring capacity (2) Fee £ (a)Not exceeding 13 cubic metres per hour
0.73 (b)exceeding 13 cubic metres per hour but not exceeding 19 cubic metres per hour
1.67 (c)exceeding 19 cubic metres per hour but not exceeding 53 cubic metres per hour
5.01 (d)exceeding 53 cubic metres per hour but not exceeding 228 cubic metres per hour
16.74 (e)exceeding 228 cubic metres per hour but not exceeding 1,600 cubic metres per hour
41.87 (f)exceeding 1,600 cubic metres per hour
100.00 ”