# The Gas (Security of Supply and Network Codes) (Amendment) (EU Exit) Regulations 2019, Paragraph 23

Extent: E+W+S+N.I.

For the text of Article 25, substitute—
“Article 25
Implementation monitoring
If immediately before IP completion day a transmission system operator has not complied with its obligations under Article 25(2) of this Regulation as it has effect in EU law, the obligations under that paragraph continue to apply.”.

---
Source: https://www.legislation.gov.uk/uksi/2019/531/schedule/3/paragraph/23 (the official version)
Page: https://openlegislation.uk/gas-security-of-supply-and-network-codes-amendment-eu-exit-regulations-2019/schedule-3/paragraph-23
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.