# The Gas (Third Party Access and Accounts) Regulations 2000, Paragraph 5

Extent: E+W+S

In section 12(6)—
(a) at the end of the definition of “gas processing facility”, there shall be added the words “and which is operated otherwise than by a public gas transporter”; and
(b) before the definition of owner, there shall be inserted—
““main commercial conditions” means—
(a) such information as would enable a potential applicant for a right to have gas processed by a gas processing facility to make a reasonable assessment of the cost of, or the method of calculating the cost of, acquiring that right;
(b) the other significant terms on which such a right would be granted; and
(c) such other information as the Secretary of State may from time to time specify by notice;”.

---
Source: https://www.legislation.gov.uk/uksi/2000/1937/schedule/3/paragraph/5 (the official version)
Page: https://openlegislation.uk/gas-third-party-access-and-accounts-regulations-2000/schedule-3/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.