# The Gate Burton Energy Park Order 2024, Paragraph 111: Arbitration

Extent: E+W

Save for differences or disputes arising under paragraphs ‎103(2), ‎103(4), ‎104 and ‎105 any difference or dispute arising between the undertaker and National Grid under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid, be determined by arbitration in accordance with article ‎40 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2024/807/schedule/14/paragraph/111 (the official version)
Page: https://openlegislation.uk/gate-burton-energy-park-order-2024/schedule-14/paragraph-111
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.