# The Gate Burton Energy Park Order 2024, Paragraph 112: Notices

Extent: E+W

Notwithstanding article 42 (service of notices), any plans submitted to National Grid by the undertaker pursuant to paragraph ‎105 must be submitted using the LSBUD system (https://lsbud.co.uk/) or to such other address as National Grid may from time to time appoint instead for that purpose and notify to the undertaker in writing.

---
Source: https://www.legislation.gov.uk/uksi/2024/807/schedule/14/paragraph/112 (the official version)