# The Gate Burton Energy Park Order 2024, Paragraph 150: As built drawings

Extent: E+W

As soon as reasonably practicable following the completion of the construction of the authorised development, the undertaker must provide to the Canal & River Trust as built drawings of any specified works in a form and scale to be agreed between the undertaker and the Canal & River Trust to show the position of those works in relation to the waterway.

---
Source: https://www.legislation.gov.uk/uksi/2024/807/schedule/14/paragraph/150 (the official version)
Page: https://openlegislation.uk/gate-burton-energy-park-order-2024/schedule-14/paragraph-150