# The Gate Burton Energy Park Order 2024, Paragraph 173

Extent: E+W

The undertaker must not under the powers of this Order acquire, extinguish, suspend, override or interfere with any rights that Tillbridge has in respect of any apparatus or has in respect of the Tillbridge Work No. 4E Area without the consent of Tillbridge, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions.

---