# The Gate Burton Energy Park Order 2024, Paragraph 14: Construction traffic management plan

Extent: E+W

(1) No part of the authorised development may commence until a construction traffic management plan for that part has been submitted to and approved by the relevant planning authority for that part, or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities, such approval to be in consultation with the relevant highway authority and West Lindsey District Council.
(2) The construction traffic management plan must be substantially in accordance with the framework construction traffic management plan.
(3) Before approving the construction traffic management plan the relevant planning authority must consult with the relevant highway authority.
(4) The construction traffic management plan must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2024/807/schedule/2/paragraph/14 (the official version)
Page: https://openlegislation.uk/gate-burton-energy-park-order-2024/schedule-2/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.