# The Gate Burton Energy Park Order 2024, Part 4: TEMPORARY MANAGEMENT OF PUBLIC RIGHTS OF WAY

Extent: E+W

(1)
Area
(2)
Public right of way
(3)
Measure (Public Right of Way to be managed during construction to maintain Public Right of Way continuity and access through the site)
District of West LindseyLL “Knai ” 44/1Public Right of Way between points PRoW-2/01 and PRoW-2/02 as shown on sheet 2 of the streets, access and rights of way plans to be managed during construction of the authorised development.
District of West LindseyLL “Mton ” 68/1Public Right of Way between points PRoW-11/01 and PRoW-11/02 as shown on sheet 11 of the streets, access and rights of way plans to be managed during construction of the authorised development.
District of BassetlawNT “Cottam ” FP1Public Right of Way between points PRoW-13/01 and PRoW-13/02 as shown on sheet 13 of the streets, access and rights of way plans to be managed during construction of the authorised development.
District of BassetlawNT “South Leverton ” BOAT16Public Right of Way between points PRoW-15/02 and PRoW-15/03 as shown on sheet 15 of the streets, access and rights of way plans to be managed during construction of the authorised development.
District of BassetlawNT “Rampton ” BOAT13Public Right of Way between points PRoW-17/05 and PRoW-17/06 as shown on sheet 17 of the streets, access and rights of way plans to be managed during construction of the authorised development.
District of BassetlawNT “Rampton ” BOAT13Public Right of Way between points PRoW-17/08 and PRoW-17/09 as shown on sheet 17 of the streets, access and rights of way plans to be managed during construction of the authorised development.
District of BassetlawNT “Rampton ” FP20Public Right of Way between points PRoW-17/12 and PRoW-17/13 as shown on sheet 17 of the streets, access and rights of way plans to be managed during construction of the authorised development.
District of BassetlawNT “Rampton ” BOAT12Public Right of Way between points PRoW-17/14 and PRoW-17/15 as shown on sheet 17 of the streets, access and rights of way plans to be managed during construction of the authorised development.
District of BassetlawNT “Rampton ” BOAT13Public Right of Way between points PRoW-17/07 and PRoW-18/01 as shown on sheets 17 and 18 of the streets, access and rights of way plans to be managed during construction of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2024/807/schedule/6/part/4 (the official version)