OpenLegislation

Article 3 Power to construct works

Original text. Later amendments are not shown.

(1)

The undertaker may construct and maintain the scheduled works.

(2)

Subject to article 4 below, the scheduled works shall be constructed in the lines or situations shown on the deposited plans and in accordance with the levels shown on the deposited sections.

(3)

The undertaker shall, within the limits of deviation, carry out and maintain such works for the benefit or protection of maritime traffic as may be necessary or expedient for the purposes of, in connection with, or in consequence of, the construction of the scheduled works.

(4)

The undertaker may, within the limits of deviation, carry out such works (of whatever nature) as may be necessary or expedient for the purposes of, or in connection with, or in consequence of, the construction of the scheduled works.