# The Gateshead (Baltic Millennium Bridge) Order 1999, Schedule 1: SCHEDULED WORKS


A 130 metre single span bridge carrying a pedestrian and cycle route across the River Tyne from a point on the south river wall 440 metres downstream of the Tyne Bridge to a point on the north river wall 450 metres downstream of the Tyne Bridge. The bridge shall rotate about its horizontal axis to allow the passage of maritime traffic through a navigable channel which has a minimum clearance of 25 metres above the level of high water for an unobstructed width of 30 metres.

---
Source: https://www.legislation.gov.uk/uksi/1999/1664/schedule/1 (the official version)
Page: https://openlegislation.uk/gateshead-baltic-millennium-bridge-order-1999/schedule-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.