# The Gatwick Airport (Northern Runway Project) Development Consent Order 2025, Paragraph 29: Soil management plan

Extent: E+W

(1) No soil removal may be carried out until a soil management plan for that soil has been submitted to and approved by CBC.
(2) Each soil management plan submitted pursuant to sub-paragraph (1) must be substantially in accordance with the soil management strategy.
(3) Removed soil must be managed in accordance with the relevant soil management plan approved pursuant to sub-paragraph (1) unless otherwise agreed in writing by CBC.

---
Source: https://www.legislation.gov.uk/uksi/2025/1054/schedule/2/paragraph/29 (the official version)
Page: https://openlegislation.uk/gatwick-airport-northern-runway-project-development-consent-order-2025/schedule-2/paragraph-29
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.