# The Gatwick Airport (Northern Runway Project) Development Consent Order 2025, Paragraph 30: Site waste management plan

Extent: E+W

(1) No part of the authorised development is to commence until a site waste management plan for that part has been submitted to and approved in writing by the relevant authority.
(2) The site waste management plan submitted pursuant to sub-paragraph (1) must include the form of sections A1, A2, A3 and A4 of Annex A to the construction resources and waste management plan.
(3) Construction waste arising from that part of the authorised development must be managed in accordance with the measures set out in the form of section A1 of the site waste management plan approved pursuant to sub-paragraph (1) unless otherwise agreed in writing by the relevant authority.
(4) A form of section A5 of Annex A to the construction resources and waste management plan must be maintained throughout the duration of the construction of that part of the authorised development and must be made available to the relevant authority upon request.
(5) In this requirement, the “relevant authority” means, in respect of a part of the authorised development—
(a) in West Sussex, West Sussex County Council;
(b) in Surrey, Surrey County Council; and
(c) partly in each of West Sussex and Surrey, West Sussex County Council (in consultation with Surrey County Council).

---
Source: https://www.legislation.gov.uk/uksi/2025/1054/schedule/2/paragraph/30 (the official version)
Page: https://openlegislation.uk/gatwick-airport-northern-runway-project-development-consent-order-2025/schedule-2/paragraph-30
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.