# The Gatwick Airport (Northern Runway Project) Development Consent Order 2025, Paragraph 5: Local highway works – detailed design

Extent: E+W

(1) No part of the local highway works is to commence until details of the layout, siting, scale and external appearance of the buildings, structures and works within that part have been submitted to and approved in writing by the relevant highway authority (in consultation with the relevant planning authority).
(2) The details referred to in sub-paragraph (1) must—
(a) be in accordance with the design principles in appendix 1 of the design and access statement unless otherwise agreed in writing with the relevant highway authority; and
(b) be in accordance with the surface access general arrangements, surface access engineering section drawings and surface access structure section drawings or otherwise demonstrate that in carrying out the part of the authorised development to which the submitted details relate the undertaker would comply with article 6 (limits of works), including detailing any reliance by the undertaker on article 6(7).
(3) The relevant part of the local highway works must be carried out in accordance with the details approved by the relevant highway authority under sub-paragraph (1) unless otherwise agreed in writing with the relevant highway authority.

---
Source: https://www.legislation.gov.uk/uksi/2025/1054/schedule/2/paragraph/5 (the official version)
Page: https://openlegislation.uk/gatwick-airport-northern-runway-project-development-consent-order-2025/schedule-2/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.