{
  "url": "https://openlegislation.uk/gatwick-airport-northern-runway-project-development-consent-order-2025/schedule-9/paragraph-88",
  "json_url": "https://openlegislation.uk/gatwick-airport-northern-runway-project-development-consent-order-2025/schedule-9/paragraph-88.json",
  "legislation": "uksi/2025/1054",
  "legislation_title": "The Gatwick Airport (Northern Runway Project) Development Consent Order 2025",
  "legislation_url": "https://openlegislation.uk/gatwick-airport-northern-runway-project-development-consent-order-2025",
  "path": "schedule/9/paragraph/88",
  "kind": "paragraph",
  "number": "88",
  "heading": null,
  "text": "Where, under this Part of this Schedule, TWUL is required to give its consent, approval or agreement in respect of any matter, that consent, approval or agreement must not be unreasonably withheld or delayed.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 9 para. 88 in force at 12.10.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1054/schedule/9/paragraph/88",
    "retrieved_at": "2026-10-28T21:11:10.827794+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}