{
  "url": "https://openlegislation.uk/great-yarmouth-third-river-crossing-development-consent-order-2020/schedule-14/paragraph-68",
  "json_url": "https://openlegislation.uk/great-yarmouth-third-river-crossing-development-consent-order-2020/schedule-14/paragraph-68.json",
  "legislation": "uksi/2020/1075",
  "legislation_title": "The Great Yarmouth Third River Crossing Development Consent Order 2020",
  "legislation_url": "https://openlegislation.uk/great-yarmouth-third-river-crossing-development-consent-order-2020",
  "path": "schedule/14/paragraph/68",
  "kind": "paragraph",
  "number": "68",
  "heading": null,
  "text": "Within 3 months of completion of the specified works and protective works (“the completed works”), the undertaker must provide to the GYPA drawings of the completed works as constructed, including the electrical and mechanical drawings of the opening and closing mechanisms of the new bridge. If any modifications are made to the completed works following their completion the undertaker must provide updated as built drawings of the modified works.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 14 para. 68 in force at 15.10.2020, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2020/1075/schedule/14/paragraph/68",
    "retrieved_at": "2026-10-28T22:24:52.073113+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}