# The Great Yarmouth Third River Crossing Development Consent Order 2020, Paragraph 13: Completion and availability of particular works

Extent: E+W+S

(1) The highway comprised in the new bridge and the new bridge western approach must not be opened for public use until the works specified in sub-paragraph (2) have been completed and made available for use.
(2) The works are—
(a) the vessel waiting facilities;
(b) Work No. 11; and
(c) Work No. 12.

---