# The Great Yarmouth Third River Crossing Development Consent Order 2020, Schedule 6: LAND IN WHICH ONLY NEW RIGHTS MAY BE ACQUIRED

Extent: E+W+S

(1) Location
(2) Plot reference number(s) shown on the land plans
(3) Purpose for which rights over land may be acquired
(4) Relevant part of the authorised development
The land plans – sheet 1
In the Borough of Great Yarmouth
In the County of Norfolk
1-02, 1-03, 1-04, 1-05, 1-06, 1-07, 1-08, 1-09
Acquisition of new rights (including the imposition of restrictive covenants) for the purpose of carrying out works to existing drainage infrastructure
Work No. 3
The land plans – sheet 2
In the Borough of Great Yarmouth
In the County of Norfolk
2-06, 2-08, 2-11, 2-12, 2-14, 2-15
Acquisition of new rights (including the imposition of restrictive covenants) for the purpose of constructing, protecting, accessing and maintaining the improved William Adams Way
Work No. 4
The land plans – sheet 3
In the Borough of Great Yarmouth
In the County of Norfolk
3-04
Acquisition of new rights (including the imposition of restrictive covenants) for the purpose of constructing, protecting, accessing and maintaining the authorised development
Work No. 6A
The land plans – sheet 4
In the Borough of Great Yarmouth
In the County of Norfolk
4-06, 4-09, 4-23
Acquisition of new rights (including the imposition of restrictive covenants) for the purpose of constructing, protecting, accessing and maintaining the authorised development
Work Nos. 6A, 6B, 7A, 7B and 8B

---
Source: https://www.legislation.gov.uk/uksi/2020/1075/schedule/6 (the official version)
Page: https://openlegislation.uk/great-yarmouth-third-river-crossing-development-consent-order-2020/schedule-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.